# Project Plan: Visual Assistant
|
||
|
||
## Introduction
|
||
|
||
This document outlines the phased development plan for the Visual Assistant project. The initial focus is on delivering a Minimum Viable Product (MVP) to provide a functional, interactive visual chatbot with persona and emotion features. Subsequent phases will introduce advanced capabilities and platform support.
|
||
|
||
---
|
||
|
||
## Development Phases
|
||
|
||
### Phase 1: MVP (Estimated: Weeks 1–4)
|
||
- Chat interface (web app)
|
||
- Persona selection
|
||
- Static PNG expressions for emotional feedback
|
||
- Expression changes driven by chat content
|
||
- User memory system for consistent behaviour
|
||
- Basic project documentation
|
||
- Unit and integration tests
|
||
|
||
### Phase 2: Enhancements (Estimated: Weeks 5–7)
|
||
- Improved emotion detection algorithms
|
||
- Custom persona creation
|
||
- User settings/preferences
|
||
- UI/UX polish
|
||
- Expanded test coverage
|
||
|
||
### Phase 3: Future Features & Platforms (Estimated: Weeks 8–12)
|
||
- Live2D model integration
|
||
- Text-to-Speech (TTS) support
|
||
- Android app development
|
||
- Cloud deployment (AWS/Heroku/Firebase)
|
||
- Monitoring and analytics
|
||
|
||
---
|
||
|
||
## Timeline
|
||
|
||
| Phase | Tasks | Duration |
|
||
|-----------|----------------------------------------|-------------|
|
||
| Phase 1 | MVP Core Features | Weeks 1–4 |
|
||
| Phase 2 | Enhancements | Weeks 5–7 |
|
||
| Phase 3 | Future Features & Platforms | Weeks 8–12 |
|
||
|
||
*Timeline is indicative and may be adjusted based on team capacity and feedback.*
|
||
|
||
---
|
||
|
||
## Milestones & Deliverables
|
||
- **End of Week 2:** Basic chat interface and persona selection demo
|
||
- **End of Week 4:** MVP feature-complete, initial documentation, and tests
|
||
- **End of Week 7:** Enhanced features and improved UX
|
||
- **End of Week 12:** Live2D, TTS, Android app, and cloud deployment
|
||
|
||
---
|
||
|
||
## Risks & Mitigations
|
||
- **Integration complexity:** Mitigated by modular architecture and regular code reviews
|
||
- **Resource constraints:** Prioritise MVP and core features
|
||
- **Platform-specific challenges:** Early prototyping and use of cross-platform tools where possible
|
||
|
||
---
|
||
|
||
## Review & Next Steps
|
||
- Regular sprint reviews (bi-weekly)
|
||
- Update plan as requirements evolve
|
||
- Track progress in TODO.md
|
||
|
||
---
|
||
|
||
*Document last updated: 17 April 2025*
|